Grab the end cap and prepare to install the 8mm Penetrator.
-
The 8mm Penetrator should have had the rigid tubing potted with the epoxy before installing it.
-
-
-
Lubricate the o-ring of the penetrator and place onto the penetrator.
-
Insert the penetrator into one of the holes on the end cap.
-
Place the nut on the backside of the penetrator and tighten to secure it in place and create a good seal.
-
-
-
Grab the 6mm penetrator that has been potted to the 4 pin cable.
-
Lubricate the o-ring for the penetrator and install back onto the penetrator.
-
Install the penetrator into the remaining hole of the end cap.
-
Install the nut onto the back side of the penetrator.
-
-
-
Using the Penetrator wrench tighten the nuts on the back of both the 6mm and 8mm penetrator
-
Make sure all of the nuts are tight to ensure that it is water tight.
-
-
-
Trim the rigid tubing and insert the 4mm take-off into the tubing.
-
Push the silicone tubing from the intake side of the peristaltic pump
-
You can use a small cable tie to secure the hoses to the 4mm Take Off to ensure that they don't come off.
-
-
-
Trim the white wire.
-
Strip the insulation from the end of the wire to prepare to install the female bullet connector.
-
Slide a female bullet connector onto the white wire.
-
-
-
Ensure the female bullet connector is inserted onto the wire correctly and crimp it into place.
-
Once crimped give the connector a tug to confirm it has been crimped on securely.
-
-
-
Trim the green wire to length and strip the insulation from the end of the wire.
-
Place a female bullet connector onto the green wire.
-
Ensure the wire is fully inserted into the female bullet connector and crimp the connector into place.
-
Once crimped give the connector a tug to ensure that it was crimped correctly.
-
-
-
Connect the red and white wires together and the black and green wires together.
-
Once the bullet connectors have been connected you can push them into the end cap to get them out of the way.
-
-
-
Place the peristaltic pump and mount onto the end cap.
-
Install 4 x M3x8mm Socket Head Cap Screws to secure the mount onto the end cap.
-
Almost done!
Finish Line